Cert Action SPR 603 Dartmouth 06032019SITE PLAN REVIEW
DARTMOUTH
PLANNING BOARD
400 Slocum Road
Dartmouth, MA 02747
TIME STAMP HERE
Page 1 of 2
CERTIFICATE OF ACTION FOR SITE PLAN REVIEW
DATE: June 17, 2019
PLAN ENTITLED: The Salty Paw – 603 Dartmouth St., Dartmouth, MA 02747
PLAN DATED: March 12, 2019 with revised SP1.1 dated 6/13/19
SUBJECT PROPERTY LOCATION: 603 Dartmouth Street
ASSESSOR’S MAP/LOT(s): Map 138 Lot 242
APPLICANT: Pam Lasher
OWNER: 603 Dartmouth Street LLC
(if different than Applicant)
This is to notify you that at its meeting of June 17, 2019, the Dartmouth Planning Board
voted to approve the above-referenced site plan. A modified Site Plan (SP1.1) and a
memorandum requesting an Exemption from Site Plan Review under §375-24.1.E (2)
was submitted June 13, 2019.
The plan sheets referred to in this action are listed below:
Title Sheet Date
Title Sheet 1 of 8 3/12/19
SP 1.1 2 of 8 4/16/19 5/23/19 6/13/19
A 1- First Floor Plan 3 of 8 3/12/19
A 2.1 – East Exterior Elevation, Roof Plan, Roof Framing Plan
4 of 8 3/12/19
A 3.1 - Building Section 5 of 8 3/12/19
A 4.1 – CMU Detail Wall Types & Eave Detail
6 of 8 3/12/19
A 5.1 – Reflected Ceiling Plan and Electrical & Switching Plan
7 of 8 3/12/19
A 6.1 – Schedules 8 of 8 3/12/19
SITE PLAN REVIEW
DARTMOUTH
PLANNING BOARD
400 Slocum Road
Dartmouth, MA 02747
TIME STAMP HERE
Page 2 of 2
The Dartmouth Planning Board voted to approve the above-referenced plans with and
exemption request the following conditions:
REQUIRED PLAN REVISIONS
1. The following Technical Reviewing Departments issues need to be addressed
to the satisfaction of the Departments prior to plan endorsement:
Refer to Project Review Comments dated May 13, 2019 (Attached Herein)
2. Any additional plan revisions required by the DPW shall be made.
3. Applicant shall submit 2 full-sized hard copy sets and an electronic plan set
(PDF & CAD) of the final plan to the Planning Office. If the plans are deemed
complete by the Planning Director, “Final Approved Plans” will be forwarded to
the building department.
4. Any substantial changes to the plan referenced in this Certificate of Action shall
require additional Planning Board review and approval. The Planning Director
shall make the determination.
A building permit shall not be issued unless a final plan has been approved by the
Planning Board, and if one is required, an occupancy permit shall not be granted by the
Director of Inspectional Services until the parking facility has been built in compliance with
the approved site plan, unless the completion of such facility is delayed by seasonal
considerations.
Approval of this plan does not imply compliance with other Town ordinances, standards,
and/or requirements administered by other Town agencies.
For the
Dartmouth Planning Board,
Christine A. O’Grady, AICP
Director of Planning